Dinawan Energy Hub

A hybrid wind, solar and battery storage energy hub in the South West Renewable Energy Zone would enable reliable, clean power to be dispatched to the National Electricity Market, offsetting electricity generation and carbon emission from ageing fossil fuel generators in New South Wales.

ABOUT THE PROJECT

The proposed ~2 gigawatt (GW) Dinawan Energy Hub would create more than 1,200 jobs during construction, and would have up to 200 wind turbines and 1.7 million solar modules, potentially providing enough clean, reliable energy to power over a million Australian homes annually. The project includes a battery energy storage system co-located with the solar farm.        

Latest updates

  • The 800 megawatt (MW) Dinawan Solar Farm with a 1,574 megawatt-hour (MWh) hybrid battery energy storage system (BESS) development application was approved by the NSW Independent Planning Commission (April 2026).
  • The Dinawan Wind Farm (stage one) bid for 357 MW was successful in Tender 4 of the Australian Government’s Capacity Investment Scheme (October 2025).
  • Spark Renewables was awarded access rights for 1,007 MW in the South West Renewable Energy Zone in New South Wales, authorising the project to apply to connect to the transmission network infrastructure (April 2025).
Capacity (1)
Proposed

Capacity

Wind farm: ~1,200 MW
Solar farm: ~800 MW (alternating current)
BESS: ~1,574 MWh

Investigation area
Investigation

area

~43,324 hectares

Houses powered
Houses

powered

~1 million annually*

Greenhouse gas potential offset
Greenhouse gas emissions

Offset

~4.7 million tonnes of CO₂ annually**

* Based on household consumption of 6 MWh per annum
** Based on capacity of 2 GW and emission factor of 0.77 tCO2e

Dinawan Energy Hub is being developed by Spark Renewables, one of Australia’s leading developers and long-term owners of renewable energy generation assets. Read more about us and our team.

LOCATION

Dinawan Energy Hub is located in the Riverina region about halfway between Coleambally and Jerilderie in the New South Wales South West Renewable Energy Zone, and on the traditional lands of the Wiradjuri people and several smaller nations of the Murrumbidgee plains.

The investigation area was designed to avoid woodland areas of weeping myall (boree), which is a protected species. The investigation area for the wind farm is 38,824 hectares with the overall wind farm footprint expected to be 1-2% of this area, and the investigation area for the solar farm is 4,500 hectares.

The project is on the route of the EnergyConnect interconnector, which will run between Robertstown, South Australia and Wagga Wagga, New South Wales. The project is strategically positioned to support the network as well as the proposed HumeLink and VNI West interconnectors.

Map of Dinawan Energy Hub - May 2025

Sharing the benefits of the Dinawan Energy Hub

Spark Renewables is committed to creating lasting benefits in the communities where our projects are developed. Our benefit sharing programs support community benefit sharing, local economic development, workforce capability, education and training, and research and innovation.

Commitment from construction & over the life of the project

$0 million

Employment and apprenticeship opportunities: stage one of the Dinawan WInd Farm 

Setting clear, measurable goals allows us to track progress, identify where additional effort or resources may be needed, and understand the positive impact our projects are making. During the development and construction of stage one of the Dinawan Wind Farm, we have committed to achieving the following workforce targets:

Local workers

25% local workers

Local trades

25% local trades

Learning workers

20% learning workers

Apprentices

10% apprentices

Women in the workforce (1)

10% women

Women in trades and apprentice

5% women in apprenticeships & trades

Underrepresented groups

20% underrepresented groups

Delivering long-term benefits for local communities

Community enhancement fund

$0 million

Our focus is to create lasting, positive change that supports the needs of each community and future local employment by establishing a community benefit sharing program for the life of the Dinawan Energy Hub. 

$25m Access fee contributions to the South West REZ

Benefits include access fee contributions for the community component, paid over 15 years and administered by the NSW Energy Corporation (EnergyCo) under the South West Renewable Energy Zone Community and Employment Benefit Program, including $9 million during stage one of the Dinawan Wind Farm.

Training & school partnerships

We are creating pathways into the renewable energy workforce through school-based initiatives, apprenticeships, industry connections and regional upskilling initiatives, including supporting the Regional Industry Education Partnerships (RIEP) and Technical and Further Education (TAFE) in NSW, with $137,932 in construction of the stage one of the Dinawan Wind Farm.

Additional support for local road infrastructure

As part of anticipated project conditions of consent we will invest at least $150,000 in local road infrastructure during construction and $50,000 during the operations of the first stage of the Dinawan Wind Farm. This is in addition to council-led critical capital works projects that the Dinawan Energy Hub will support through the Voluntary Planning Agreement.

Community funding

The Dinawan Energy Hub will provide over $34 million in direct community funding through a Voluntary Planning Agreement (VPA) with local councils, and separate community funds supporting local priorities, neighbours and First Nations people.

Critical Capital Works Fund

Community Benefit Fund

Neighbour Benefit Fund

Aboriginal Benefit Fund

Supporting domestic clean energy and technology supply chains

Local business and supply chain

$0 million

Local procurement creates stronger social value when smaller businesses can realistically participate. More than $26 million will support the delivery of targeted local work packages, capability-building initiatives, and research and innovation programs across the Dinawan Energy Hub.

$9.1m of Access fee contribution

Benefits include South West REZ access fee contribution to support employment initiatives, paid over 15 years and administered by EnergyCo, including $3.2 million during stage one of the Dinawan Wind Farm.

$3.5m on Local economic development

A locally based capability hub and a dedicated regional development program, valued at $1,259,804 during construction of stage one of the Dinawan Wind Farm, will support local businesses in building capability and participating in Dinawan Energy Hub contract opportunities.

$1.9m for Research and innovation funds

The Dinawan Energy Hub will provide funding for two programs delivered in partnership with universities to advance sustainability outcomes in the circular economy, social impact and recycling technologies, including $681,545 during the first five years of stage of the Dinawan Wind Farm.

$0.2m Women in Clean Energy Network & Scholarships

Focused on the Riverina region, this program will distribute $81,136 during stage one of the Dinawan Wind Farm to support career development scholarships for women in the renewable energy sector, establish a dedicated mentoring network, and provide access to support services addressing domestic and family violence and sexual harassment.

$2.9m Dinawan Centre of Excellence

As well as providing operational facilities, this centre will also create opportunities for education, research, innovation and community participation. It will support partnerships with local projects, universities and research institutions, and host training, workshops, seminars and site visits

$9.2m Local Manufacturing

Spark Renewables has also committed to support the procurement of wind and solar farm components manufactured locally, subject to suitable capacity being available.

Commitments to sourcing local content during stage one of the Dinawan Wind Farm 

This includes delivering civil works, logistics, turbine erection and commissioning support, balance of plant, accommodation and project services.

Percentage of total steel products and components to use locally milled steel:
Steel

0%

Percentage of pre-operational spending on locally sourced goods and services:
Construction

0%

Percentage of operational spending on locally sourced goods and services:
Operations

0%

Future opportunities at stage one of the Dinawan Wind Farm

The application process, including requirements and registration channels such as ICN Gateway and Supply Nation, will be confirmed as part of the procurement plan and will depend on the major contractors appointed for equipment supply and installation and balance of plant services. These opportunities are still to come and will be announced publicly in due course. In the meantime, interested businesses can sign up to receive notifications about tender opportunities and capability-building programs.

First Nations Partnership for training and workforce development

Local supply innovation

$0 million

with 85% spent in the first five years of each project stage

Achieving First Nations participation requires more than passing targets on to contractors. Structural barriers and varying contractor capability can make it difficult to recruit workers. Our approach is deliberate, culturally informed and locally grounded with partnerships focussed on mentoring, employing and retaining First Nations workers over the long term.

First Nations participation targets: stage one of the Dinawan Wind Farm

Spark Renewables is committed to engaging First Nations-owned businesses and employees in its renewable energy projects wherever possible. We measure the impact on local employment and investment at our projects.

0%

Percentage of First Nations workers during development

0%

Percentage of First Nations workers during construction

0%

Percentage of First Nations workers during operations

$0M

Procurement during development, construction & operations 

0%

Target for project employees to complete cultural competency training

Partnership approach

The partnership approach, working with established Aboriginal organisations will address common barriers to First Nations employment and retention, with support linked to work packages, contractor requirements and reporting. During stage one of the Dinawan Wind Farm, a contribution of $972,967 across ten commitments will support attracting, developing, and retaining First Nations workers - providing them with the tools and support to build a long-term career. It will also support cultural activities throughout the life of the project, including events such as NAIDOC celebrations and smoking ceremonies at key project milestones.

Knowledge, culture & art on country

Spark Renewables recognises the social, cultural and economic importance of First Nations stewardship and the enduring connection of Aboriginal and Torres Strait Islander peoples to Country. First Nations culture will be incorporated into key project milestones and activities, including smoking ceremonies and other culturally significant events on Country.

Capacity & dedicated resources

A strong local presence will support locally led engagement, recruitment, screening and mobilisation of surrounding community members into project employment. Dedicated workforce support will also connect workers with services that help address barriers to retention, including mental health and wellbeing support, health programs and other practical assistance.

Scholarships & training

A strong local presence will support locally led engagement, recruitment, screening and mobilisation of surrounding community members into project employment. Dedicated workforce support will also connect workers with services that help address barriers to retention, including mental health and wellbeing support, health programs and other practical assistance.

Recruitment & skills pathways

First Nations trainees and employees will receive ongoing mentoring, wellbeing support and structured skills development throughout their employment. This program will be delivered with contractors and linked to clear employment pathways, including opportunities to transition into longer-term roles beyond construction.

PROJECT NEWS

To receive regular updates about the project, please subscribe here.

PLANNING & CONSULTATION

Project status: Dinawan Solar Farm approved and Dinawan Wind Farm's Response to Submissions under assessment by the DPHI

The proposed Dinawan Energy Hub is considered State Significant Development under NSW planning legislation. The NSW Department of Planning, Housing and Infrastructure (DPHI) will assess the development application documents and the consent authority will be the Minister for Planning or the Independent Planning Commission (IPC).

Scoping Reports for the Dinawan Solar Farm and for the Dinawan Wind Farm were lodged with the DPHI in November 2022. The Scoping Reports outline the proposed project in more detail and identify important issues that will require further assessment, consultation and technical studies. The DPHI issued its requirements, known as Secretary’s Environmental Assessment Requirements (SEARs) on 14 December 2022. The SEARs are addressed in a comprehensive Environmental Impact Statement (EIS) for each project. These documents can be viewed on the DPHI Major Projects website by searching for "Dinawan Solar Farm" and "Dinawan Wind Farm".

The EIS for the Dinawan Solar Farm was submitted in November 2023 and was on public exhibition in December 2023. The exhibition phase is a crucial step in the planning approval and assessment process, providing an opportunity for the community to examine comprehensive project plans and share their feedback by making submissions. The Response to Submissions was completed and submitted in September 2024 followed by a Recommendation (subject to Conditions of Consent) that was made by the DPHI in December 2025. The Dinawan Solar Farm received approval in April 2026.

Formal NSW planning process

Wind farm
Solar farm
Proposal announced ✓

To industry, government and community

Scoping reports ✓

Community consultation and preliminary technical studies 

SEARs issued ✓

Secretary's Environmental Assessment Requirements

EIS preparation ✓

Community engagement and technical studies to inform the EIS and SIA

EIS submission and exhibition ✓

Public exhibition for agency and community comment

Response to submissions ✓

Addressing comments and issues raised about the EIS in a "Response to Submissions" report

Assessing the proposal

Assessment by the DPHI

Determination

The Minister for Planning or the Independent Planning Commission decides the proposal

Approved

Development Application status

Community consultation

As part of the planning and development process, we are undertaking extensive consultation with the community, stakeholders and Traditional Custodians of the land. The consultation will take place via community drop-in sessions, community briefings, surveys, one-on-one meetings, newsletters, our project website, and social media. We encourage all stakeholders and community members to get involved. Find out more and have your say:

  • Sign up to newsletters.
  • Request a one-on-one meeting or call.
  • Provide feedback via surveys.

Questions & complaints

 

If you have questions, feedback or complaints, please leave a message at 1300 271 419 to speak to one of the Spark Renewables team or email info@dinawanenergyhub.com.

TIMELINE

Step 1 - complete

Project identification ✔

2021-2022

Step 2 - complete

Initiate community consultation and preliminary studies ✔

2021-2022

2023

Step 3 - complete

Environmental Impact Statement ✔

2023

2024-2026

Step 4 - in progress

Access rights - Dinawan Wind Farm & Dinawan Solar Farm ✔
Capacity Investment Scheme (Tender 4) - Dinawan Wind Farm (stage one) ✔
Planning: Dinawan Solar Farm approved ✔
Dinawan Wind Farm under assessment in progress

2024-2026

2026-2027

Step 5

Final investment decision

2026-2027

2027-2029

Step 6

Construction

2027-2029

2029 onwards

Step 7

Operations

2029 onwards